May 13 Construction Update


? Work on the underground pipe loop is finishing up behind the IT and BT buildings

? Continue to use caution in the area between BT and IT

? A walking path is now cleared between IT and the Whatley Center

? A temporary sidewalk is being placed behind the Admin building in anticipation of upcoming renovations


? Work will be moving inside several buildings very soon

Construction update for April 29

? Work continues in the area behind BT and near the welding/auto body shop.



? The water leak last week slowed down progress slightly, but the project remains ahead of schedule.

? We do not anticipate any major changes to the construction pattern over the next week.

? Building construction will kick off in early June

? Those who work in Humanities should start working with supervisors to plan the move from that building.

April 15 Construction Update


? Work is currently moving to the area behind BT and near the welding/auto body shop.

? The back two doors of the BT building and the parking lot between IT and the welding/auto body shop are closed for the time being.

? There will be no through passage between IT and the Whatley Center for approximately two more weeks.

? Please use caution on that entire side of campus and look out for heavy machinery and workers.


Construction update April 7


    \t
  • There is now a walkway connecting the BT/IT buildings and the Whatley Center. However, please continue to use caution in this area as construction on the underground loop continues.

  • \t
  • You can follow the construction progress online at†www.ntcc.edu/construction.


Plan Ahead! The entire parking lot behind UHS around to the SUB†will be closed May 16 to June 4†as they work to install a new drain system.†

March 17 construction update


    \t
  • The construction project remains on schedule as the crews work to lay the underground piping and electrical conduits around campus

  • \t
  • The area between Student Services (Admin) and the LRC will remain blocked off for the next week

  • \t
  • While progress is going well so far, weather may continue to be an issue in the coming weeks

  • \t
  • You can follow the construction progress online at†www.ntcc.edu/construction.

March 3 Construction Update



    \t
  • Power will be cut off in the Administration building beginning at 1 p.m. Friday afternoon

  • \t
  • Expect to see demolition starting early this Friday between the BT and IT building up to the walkway.

  • \t
  • Please DO NOT park in the lot between IT and Welding Friday, as demolition will begin sometime tomorrow.

  • \t
  • Construction will continue from the IT/BT area around the LRC during spring break.

Construction Alert

Northeast Texas Community College experienced a brief power outage in several buildings Tuesday morning caused by a construction related incident. Power was restored in all buildings except Humanities, which remains without power for the time being. Students who have classes in the Humanities building should report to their classrooms as regularly scheduled and new arrangements will be made at that time.